Having received just two engines so far, it has been learnt that HAL is set to deliver the first two Tejas Mk1A units in October.

HAL is set to deliver the first two Mk-1A aircraft in October, sources said.
Hindustan Aeronautics Limited (HAL) has only received 2 GE engines for the Tejas Mk1A this year, falling short of the planned 12 by year-end. According to sources, the aerospace and defence company was expected to receive two more engines in August, but these deliveries did not occur.
With this delay, there are concerns about meeting the 12-engine target by 2025.
Having received just two engines so far, it has been learnt that HAL is set to deliver the first two Tejas Mk1A units in October.
Before being inducted next month, the two jets will undergo weapons firing tests this month.
According to a senior HAL official, the delivery schedule for the 83 Tejas Mk1A jets has already slipped by at least four quarters.
Akash Sharma, Defence Correspondent, CNN-News 18, covers the Ministry of Defence and Ministry of Railways. In addition, he also follows developments in the national capital. With an extensive experience coverin...Read More
Akash Sharma, Defence Correspondent, CNN-News 18, covers the Ministry of Defence and Ministry of Railways. In addition, he also follows developments in the national capital. With an extensive experience coverin...
Read More
- Location :
- First Published:
September 04, 2025, 07:25 IST
News india HAL Set To Deliver 2 Tejas Mk1A In October, Despite Delays In Deliveries: Sources
Disclaimer: Comments reflect users’ views, not News18’s. Please keep discussions respectful and constructive. Abusive, defamatory, or illegal comments will be removed. News18 may disable any comment at its discretion. By posting, you agree to our Terms of Use and Privacy Policy.
Read More