Mumbai-Ahmedabad Bullet Train project: NHSRCL releases plan for 16 km tunnel construction

1 hour ago 6
ARTICLE AD BOX

3 min readUpdated: Apr 9, 2026 11:44 AM IST

 NHSRCL)Mumbai-Ahmedabad Bullet Train: TBM assembly begins for 16 km tunnel (Image: NHSRCL)

Mumbai-Ahmedabad Bullet Train project: The National High Speed Rail Corporation Limited (NHSRCL) has released plan to construct a 16-km-long tunnel as part of the Mumbai-Ahmedabad bullet train project. Spanning 508 km, this is India’s first high-speed rail corridor, passing through Gujarat, Maharashtra and the Union Territory of Dadra & Nagar Haveli.

Mumbai-Ahmedabad bullet train tunnel

It plans to construct a 21-km-long tunnel for the Mumbai-Ahmedabad High Speed Rail (MAHSR) project between Bandra Kurla Complex (BKC) and Shilphata in Maharashtra. The tunnel will also include the country’s first 7-km-long undersea stretch beneath Thane Creek.

Of the total 21 km, 5 km of tunnelling using the New Austrian Tunnelling Method (NATM) has already been completed, while the remaining 16 km will be constructed using Tunnel Boring Machines (TBMs). According to NHSRCL, the lowering and assembly of the TBM has now commenced for the 16 km tunnel section between BKC and Sawli (near Ghansoli).

How NHSRCL plans 16 km tunnel for bullet train

The 16 km tunnel will be a single tube tunnel of 13.1 m diameter to accommodate twin track. This tunnel will be about 25 to 57 Meters deep from the ground level and the deepest construction point will be 114 m below the Parsik hill.

“The process began with the lowering of one of the six segments of the main shield, weighing approximately 170 metric tonnes. This segment measures about 8.66 metres in length and approximately 7 metres in width and was lowered at a depth of 56 metres below ground level—equivalent to a 20-storey building, at Vikhroli, Maharashtra,” the NHSRCL said.

NHSRCL has received two Tunnel Boring Machines (TBMs), with tunnelling operations set to begin after thorough testing and commissioning. To lower the TBMs, three shafts have been constructed:

  • Shaft 1: Retrieval shaft at BKC
  • Shaft 2 in Vikhroli
  • Shaft 3 in Sawli (near Ghansoli)

TBM 1 will start from Shaft 2 at Vikhroli and will move towards Shaft 1 of Mumbai Bullet Train station at BKC while TBM 2 will start from Shaft 3 at Sawli and move towards Vikhroli.

Story continues below this ad

“A dedicated casting yard covering an area of 11.17 Ha for casting tunnel lining for the 16 km TBM portion is already operational in Mahape, Thane district. 77,000 segments will be cast to form 7,700 rings. Special ring segments are being cast for the tunnel lining, each ring comprising nine curved segments and one key segment, with each segment being 2 meters wide and 0.5 meters (500 mm) thick,” it added.

Tunnel Boring Machine (TBM) Technical Specifications

95.32 m

Length of Each TBM

TBM Specifications

Weight of TBM 1: 3080 tons

Weight of TBM 2: 3184 tons

Cutter head diameter: 13.6 m

TBM type: Mix Shield / Slurry based

Main Components

Cutter wheel, Main bearing, Jaw crusher

Erector, Main shield, Tail Shield

Gantry 1-4 with specialized functions

Gantry Systems

Gantry 1

Transformers, Operator cabin, grouting pump, STS

Gantry 2

Segment lifter, grout tank, hose wheel

Gantry 3

STS Pipe wagon, Cable box

Gantry 4

Ventilation duct

Performance & Timeline

Speed: Max 4 RPM (revolutions per minute)

Max excavation rate: 49mm/min

TBM initial drive: July 2026

Main drive: October 2026

Source: NHSRCL

Express InfoGenIE

Anish Mondal is a journalist with over nine years of experience covering the railways and roadways. Currently a member of the Indianexpress.com editorial team, Anish specializes in high-impact sectors. Professional Journey Anish began his career at the public broadcaster Rajya Sabha Television (now Sansad TV), where he developed a foundational understanding of legislative processes and national governance. In 2018, he transitioned to digital financial journalism at FinancialExpress.com, spending nearly six years refining his expertise in market trends and corporate reporting. Before joining The Indian Express in 2025, he served as a key contributor at ETNowNews.com. Education & Expertise Anish’s reporting is backed by a rigorous academic background in communication and the humanities: Master of Journalism and Mass Communication (MJMC) – Apeejay Stya University Post Graduate Diploma in Journalism and Production (PGTVRJP) – Apeejay Institute of Mass Communication Bachelor of Arts (English Honours) – University of Calcutta Areas of Coverage Connectivity: Detailed reporting on the expansion of Indian Railways and National Highway networks. ... Read More

Stay updated with the latest - Click here to follow us on Instagram

© IE Online Media Services Pvt Ltd

Read Entire Article